In its original form, it is a free-flowing mixture. Before application thermoplastic must be melted. To ensure that all polymers are completely melted and homogenized, after achieving the operating temperature of the melt (190-210 °C), the material must be mixed in the heater at the same temperature for 1.5 hours before application. Apply in dry weather onto a dry road surface that is
free of dirt, dust, sand and oil at a steady ambient temperature of min +5 °C to max. +30 °C and max. 80% relative humidity. The road surface temperature must be above +10 °C. It is recommended to allow new road surfaces/new surface treatments to weather for two months before marking, otherwise paint can be prone to yellowing. It is not recommended to apply paint onto asphalt concrete
road surfaces if over 50% of the total surface area exhibits bitumen bleeding/flushing. The best thermoplastics consumption is approximately 6.5 kg/m2, depending on the road class/traffic intensity, road surface condition, line types, and surface treatment.
Glass bead consumption: at least 300 g/m2.